In cases of conflict between general and specific requirements, which requirement takes precedence?

  1. General requirement

  2. Specific requirement

  3. Neither requirement

  4. Both requirements apply equally

The correct answer is: Specific requirement

In situations where there is a conflict between general and specific requirements, the specific requirement takes precedence because it is designed to address particular situations or conditions that may not be adequately covered by the more general guidelines. General requirements are broader and cover a wider range of scenarios, while specific requirements provide detailed instructions or criteria tailored to a particular case or context. Therefore, if there is any ambiguity or potential inconsistency between these two levels of requirements, the specific requirement is prioritized to ensure that the unique circumstances are met effectively. This principle is crucial in regulatory and compliance contexts, where precise standards are necessary to ensure safety, legality, and adherence to best practices.